CONSTRUCTION COST |
|
ESTIMATED CONSTRUCTION COST OF THE PENDING WORK OF THE ALIPORE HOSPITAL AS ON 31ST MARCH, 2004 | ||||
| No. |
Description of the work pending at the ALIPORE SOCIAL WELFARE TRUST'S ALIPORE HOSPITAL CAMPUS |
Est. Cost |
Total Estimated Pending Cost (in Indian Rupees) |
PAYMENT PENDING on WORK COMPLETED |
| 1 | Structure: R.C.C. Structure and plastering work of Interior and exterior of the building is completed | 90 Lacs | Work Completed | NIL |
| 2 | Plumbing: Work in progress … | 10 Lacs | Work Completed | 10,000 |
| 3 | Flooring: a)
Materials. b) Labour… |
20 Lacs 7 Lacs |
Work Completed | NIL |
| 4 | Tiling Work: a) Materials b) Labour |
15 Lacs 4 Lacs |
Work Completed | 45,000 1,12,000 |
| 5 | Electrical Fixtures: a) Wiring and Fittings b) Tube lights (140) c) Fans (150) d) Air-conditions (11) e) Accessories f) Labour |
3.00 Lacs 0.60 Lacs 1.50 Lacs 3.40 Lacs 1.10 Lacs 0.80 Lacs |
Work Completed | 45,000 |
| 6 | Elevators: Provision is for two hospital lifts, but for the
time-being we are opting for one elevator and then whenever necessary we
shall go for second one which shall cost
Rs. 3.79 Lacs. a) Contract with the company b) Labour and materials |
2.99 Lacs |
Work Completed | NIL |
| 7 | Landscaping: | 3 Lacs | 50,000 | NIL |
| 8 | Quarters: for Class IV workers (Interest Donations is accepted) |
14 Lacs | 9,00,000 | NIL |
| 9 | Wooden Doors, Aluminum section windows and Grills: a) Doors (165) b) Aluminum Sections Windows c) Iron Grills (125) d) Accessories e) Labour |
3,15,000 2,50,000 75,000 14,000 60,000 |
5,000 | 50,000 |
| 10 | Washroom (Interest Donations is accepted) | 50,000 | 10,000 | 30,000 |
| 11 | Incinerator Room (Interest Donations is accepted) |
63,000 | 63,000 | NIL |
| 12 | Clothes-Drying Room (Interest Donations is accepted) |
50,000 | 15,000 | NIL |
| 13 | Motor Room | 63,000 | Work Completed | NIL |
| 14 | Electricity Control, Switch and Meter Room |
73,000 | Work Completed | NIL |
| 15 | Generator Room | 73,000 | Work Completed | NIL |
| 16 | Compound Wall
(Interest Donations is accepted) |
7,00,000 | 3,00,000 | NIL |
| 17 | Prayer Hall [exterior] (Only Lillah Donations are accepted) |
1,80,000 | 1,80,000 | NIL |
| 18 | Drainage, Sewerage etc. (Interest Donations is accepted) |
7,00,000 | Work Completed | 30,000 |
| 19 | Waterproofing | 4,50,000 | Work Completed | 50,000 |
| 20 | Streetlights, Floodlights, etc. (Interest Donations is accepted) |
35,000 | 35,000 | NIL |
| 21 | Painting: a) Interior 3,05,000/- b) Exterior 4,25,000/- |
7,30,000 | Work Completed | 50,000 |
| 22 |
Public
Toilets (for Males & Females) (Interest Donations is accepted) |
1,30,000 | 1,30,000 | NIL |
| Total Estimated construction Cost and Work and Payment Pending on Work Completed at Alipore Hospital | 217.3 Lacs | 16,88,000 | 3,92,000 | |
|
Total Work Pending Cost Rs. 16,88,000=00 | ||||
| ASWT request all of you to come forward and contribute generously and motivate others to contribute for this noble cause to serve Mankind. ASWT also extends its gratitude to all those who has been instrumental to complete this project. | ||||